Statement By Ghana Gas On The Status of Commissioning Activities at the Gas Infrastructure Project

In fulfillment of our commitment to continuously update the Ghanaian public and ourDr-Kwesi-Botchwey Statement By Ghana Gas On The Status of Commissioning Activities at the Gas Infrastructure Project key stakeholders on the operations of the Atuabo Gas Processing Plant and associated facilities during the ongoing Commissioning Stage, the Board of the Ghana National Gas Company (Ghana Gas) can confirm that we are currently supplying the Volta River Authority (VRA) with gas at 50-53 million standard cubic feet per day (50-53MMSCFD), which is generating between 150-200 MW of power at Aboadze.

Aboadze is therefore currently relying solely on gas from Atuabo to power the various plants in the enclave, and we are looking to ramp up flow from the current average of 50MMSCFD to the design flow of 150MMSCFD by end of this month (December 2014). Our current permits from the Energy Commission and Petroleum Commissions allow us to flow up to 150MMSCFD.

To reach that flow level, the VRA is expected to confirm its readiness to take the higher flows. The absence of enough functioning generating units at the VRA enclave in Aboadze and compressor trippings on the offshore facility, FPSO Kwame Nkrumah, are two key issues Ghana Gas has been concerned about. We are accordingly in discussions with VRA and Tullow Oil respectively to address these challenges. Indeed, since the commencement of commissioning on November 10, 2014, supply of raw gas from Tullow Oil has been sporadic.

Ghana-gas Statement By Ghana Gas On The Status of Commissioning Activities at the Gas Infrastructure ProjectMost of the upstream flow curtailment incidents have resulted from unplanned outages or trips of the FPSO gas export compressor. The outage periods have ranged from 30 minutes to as long as 7 hours. These have gravely affected our commissioning schedule.

We have, thus far, also produced from the Atuabo Plant, 3,000 tons of LPG, out of which 2,100 tons have been delivered to the market for use. The plant has also produced over 500tons of condensate out of which about 300tons has been transported to the market. These levels would increase significantly as we near completion of the commissioning process and as we increase raw gas intake at the Atuabo Plant.

The Board is generally pleased with the overall commissioning processes and looks forward to a successful completion and commencement of full operations.

KWESI BOTCHWEY

This post has already been read 1188 times!

Kenneth Ashigbey is the Chief Servant of the Ghana Chamber of Telecommunications, is a great believer in Ghana & believes that with right Leadership in all aspect of Life within Ghana, we will hit the very top. I believe that Leadership is not just Political leadership but Leadership in very aspect of the word. Lets all shine in our corners where we are. We should also support each other as Ghanaians 1st before extending our hands to strangers. We should allow the Princes of Land to marry the Land not Strangers 1st.